Friday, June 25, 2010

~25th June 2010~

Had a short meeting with both dierectors of the infrastructure department to discuss what we had learned from the 12 weeks of training.

Bid farewell to all the other staffs in Zaidun-Leeng and thanked them for all the patience they gave us and knowledge they could share with us.

Thursday, June 24, 2010

~24th June 2010~

Followed Mr. Law to landfill for the monthly site meeting at Sua Betong, Port Dickson, Negri Sembilan.

I also went to Bukit Palong landfill closure site for site inspection of works done on site.

Wednesday, June 23, 2010

~23rd June 2010~

Did colouring and folding for a project's drawing before submission to the local authority.

Tuesday, June 22, 2010

~22nd June 2010~

Went to do site reconnaissance survery at Kota Damansara. A total of 3 locations have been surveyed:-
a) A stream that was proposed to be converted into a large main pond.
b) 2 ponds that to be desilted.


We took photos of the surroundings and identify any problems that might/will occur during construction.

Monday, June 21, 2010

~21 June 2010~

 Prepared the landfill site visits report for final report of Industrial Training.

Requested so informations about the landfill from Mr. Law and ask any questions about any uncertainties.

Friday, June 18, 2010

~18th June 2010~

Followed Mr. Law to 3 landfill sites - Pajam, Bukit Palong and Sua Betong located in Negri Sembilan.

Thursday, June 17, 2010

~17th June 2010~

Went to a construction site at Taman Melawati to observe the hand-dug Caisson on a hill slope where is enaccessible by lage machines to do pilling.

Get to know how hand-dug Caisson is constructed with the method statement provided by GEOHAN Sdn. Bhd., a specialist in all types of pillings including hand-dug Caisson.

Tuesday, June 15, 2010

~14th June - 16th June 2010~

Continued with the drainage design calculation.

Highlighted ou the high points and the low points to determine the flow path of the water through the landfill.

Plateau drain and berm drain are not requuired to design as it will be constructed based on the site condition by the contractor.

To determine the size of the drains required, the total catchment area of the length of the drain have to be identify.

By using "Urban Storm Water Management Manual for Malaysia (Manual Salirann Mesra Alam Malaysia)", the size of the drain can be calculated.

(Kg. Mat Kilau Landfill, Jerantut, Pahang)

Friday, June 11, 2010

~11th June 2010~

Followed Mr. Haizal to a construction site at Balai Seni Malaysia for site visit.

Mr. Haizal explained to us about the drainage project that hs is incharge with.

Met a resident engineer, Mr. Ng Keng Wai on the site and he brought us into the structure construction building to have a look at the progress and explained about the structure and some faulty works done by the contractor.

Thursday, June 10, 2010

~10th June 2010~

Assists Mr. Haizal on drainage design for a landfill site located at Mat Kilau, Jerantut, Pahang.

Determined the layout of the drainage path and indicated the invert level of each sump.

Wednesday, June 9, 2010

~9th June 2010~

Worked on the level monitoring for 2nd Apron cargo of Penang International Airport.

Produced a clearer indication of settlement status in an A2 size layout plan.

Tuesday, June 8, 2010

~8th June 2010~

Finalised the pump station's calculation report for 2 different height of pump station.

=> 3.5m height and 2.5 m height pump station.

Printed out and ready for Ir. Ng Keng Keong to certify with his Professional Engineer's stamp and signature on the calculation report.

Monday, June 7, 2010

~7th June 2010~

Visiting Supervisor, Dr. Abdullahi came to Zaidun-Leeng Sdn. Bhd. to evaluate us and met with Ir. Ng Keng Keong, Infrastructure depertment's director to discuss the progress of the trainees for the past 2 months.

Continued to assist Mr. Law on the pump station's reinforced concrete wall calculation

Thursday, June 3, 2010

~3rd June - 4th June 2010~

Assists Mr. Law in the pump station calculation report (taking the moment assuming the wall of the pump station is cantilever supported).

=> Pumpt stations of 3.5m height and 2.5 m height.

Tuesday, June 1, 2010

~1st June - 2nd June 2010~

Read and study the book "Swimming Pool" borrowed.

Monday, May 31, 2010

~31st May 2010~

Borrowed a book on "Swimming Pool" by P.H. Perkins from Zaidun-Leeng's library under the recommendation of Ir. Ng. Keng Keong.

Followed Mr. Lay to Rawang for the double-storey terrace house's site meeting.

Friday, May 28, 2010

~28th May 2010~

Public Holiday

:: Wesak Day ::

Thursday, May 27, 2010

~26th May - 27th May 2010~

Ir. Ng Keng Keong gave us some information and knowledge about how a swimming pool functions from pump house to the pool and back to the pump house through the balancing tank and sand filtration system.

Read about the pumps used in a swimming pool system.

Leakage problem occured at Tropicana Golf  & Country Resort's swimming pool where ponding of water can be seen when the pump is turned on.

Ir. Ng Keng Keong then requested us to study on the pipeline layout plan and to colour the pipes with different colours to show how the pipe is connected to each other.

Monday, May 24, 2010

~24th May - 25th May 2010~

Prepared a reporyt for the pump house visit last Wednesday at Taman Saujana Hijau, Prescint 11, Putrajaya.

Friday, May 21, 2010

~21st May 2010~

Read and study about the pumps used for irrigation purposes from Grundfos Catologue

Thursday, May 20, 2010

~20th May 2010~

Did colouring and folding for a project submission.

Wednesday, May 19, 2010

~19th May 2010~

Studied the temporary earth drain (TED) design calculation report done by Mr. Law.

Followed Ir. Ng Keng Keong to check on the leaking problem that occured in the pump house at Taman Saujana HIjau in Prescint 11, Putrajaya.

Monday, May 17, 2010

~17th May - 18th May 2010~

Helped Mr. Law to doublecheck any errors in the structural drawings for the draughter to do correction on it before printing to the actual size of paper required (A1) size for tender drawing.

Do exercise using Hazen-William formula to determine the nominal diameter swize to be used for the water supply pipe for Bandar Sri Damansara.

Friday, May 14, 2010

~14th May 2010~

Followed Mr. Law to site meeting at Rawang for the double-storey terrace house project.

Ir. Lim Guan Hock shared with us some of the knowledge about sewerage and water system in an area

Thursday, May 13, 2010

~13th May 2010~

Edited the water demand computation requested by Ir. Lim Guan Hock.

Assisted Mr. Lay in checking of the column schedule for the double-storey terrace house project.

Wednesday, May 12, 2010

~12th May 2010~

Went to 3 landfill site - Pajam, Bukit Palong and Sua Betong, all which are located in Negri Sembilan together with 2 engineers.

Monday, May 10, 2010

~10th May - 11th May 2010~

Calculated the water demand for Bandar Sri Damansara of each zone - High Zone, Medium Zone and Low Zone and typed it out in a table format

Friday, May 7, 2010

~7th May 2010~

Calculated the water demand for Bandar Sri Damansara's Medium Zone today.

Thursday, May 6, 2010

~6th May 2010~

Prepared a simplified 2 page report for the apron's settlement for easier and more convenient way to identify the critical locations whereby the settlement increases every fortnight based on the survey settlement report.

Wednesday, May 5, 2010

~5th May 2010~

Was given a book of report for the fortnight settlement readings of Penang International Airport's apron

We were requested to identify the location of the readings taken. There are a total of N locations where every fortnight the surveyor will take the settlement reading for a duration of 6 months.

Monday, May 3, 2010

~3rd May - 4th May 2010~

Drew the cross-section of the detention pond using the levels surveyed by the surveyor and the proposed level on the same sheet of paper so as to able to calculate the volume of cut/fill.

Ir. Ng Keng Keong shared some knowledge about civil engineers and the society based on his experiences of being an engineer.

Friday, April 30, 2010

~30th April 2010~

Followed Mr. Law to a site meeting at Rawang for the double-storey terrace house project.

The site meeting was about the show house.

Thursday, April 29, 2010

~29th April 2010~

Prepared report for the site visit which include brief explanation of the site condition using the photos taken at the actual site.

Wednesday, April 28, 2010

~28th April 2010~

Went for site survey at Bandar Sri Damansara.

Location 1. Sector 'B' Sri Damansara
- to verify the types of buildings in the area so as to enable calculation of the total water demand for that area

Location 2. Persiaran Perdana
- to survey the actual site condition and taken a few photos at different spot along Persiaran Perdana.

Tuesday, April 27, 2010

~27th April 2010~

Went through the layout plan of Sri Damansara Sector 'B' and calculated the total water supply demand for that area.

Divided the area into several sub-area so as to have a clearer picture of the actual location for tomorrow's site survey.

Studied through Mr. Law's pumphouse calculation report where used yield line design method to calculate the moment acting on the wall of the pumphouse.

Monday, April 26, 2010

~26th April 2010~

Measured the length of road curb, the area of walk path, road resurfacing and road widening for the calculation of cost for upgrading the main road along Persiaran Perdana at Bandar Sri Damansara.

Wednesday, April 21, 2010

~21st April - 23rd April 2010~

These days are used to continue with the remaining beams checking of the double-storey terrace house project.

Tuesday, April 20, 2010

~20th April 2010~

Today I measured the length and calculate the area for an earthwork project, i.e. length of berm drain, length of hoarding, length of temporary earth drain, are of cut/fill and etc.

The measured values are to be inserted for BQ purpose to estimate the overall project cost.

Monday, April 19, 2010

~19th April 2010~

Ir. Lim Guan Hock briefed us through about the renovation work to be done for the main terminal building (MTB) of the Penang International Airport for expansion purposes.

The infra department is in-charge of relocating the existing water and sewer lines for the expended MTB.

Ir. Lim requested me to identify the existing washroom locations and the sewer and water pipes going through MTB by using different colours to illustrate it.

With this illustration, we were able to create a new pipeline for those pipes that are affected from the works.

Friday, April 16, 2010

~13 April - 16 April 2010~

Double-Storey Terrace House Project at Rawang

After completing load distribution on each beams, started calculating the load acting on each beams such as wall load, self-weight of beam, slab load, etc. With all the load acting on each beam calculated, max moment acting on the beam can be calculate then the reinforcement steel bars required can be calculate using BS8110: Part 1:1997 Clause 3.4.4.4.

Checking of each beam of every floor, i.e. ground floor beams, first floor beams, roof beams and upper roof beams.

Monday, April 12, 2010

~12 April 2010~

Today whole day checking the beam size and reinforcement steel bars for a beam of a double-storey terrace house. Basic requirement is to come out with the bending moment diagram to show how the moment is distributed and identify the maximum moment acting on the beam. Due to basic knowledge is not strong enough, it takes the whole day to just calculate the it. Finally manage to calculate it and found that the original design was under-design. Will check again tomorrow to confirm correct or not my calculation.

*All calculation are done by manual (hand) calculation due to my department is infra department, meaning that we don't have structural software in our department.

Sunday, April 11, 2010

Basic Info

T12 means high tensile deformed reinforcement steel bar with characteristic yield strength of 460 N/mm² of 12mm diameter.

R12 means mild steel round bar with characteristic yield strength of 250 N/mm² of 12mm diameter.

Water evaporation rate in Malaysia (drought season) = 6 mm/day

Saturday, April 10, 2010

1st Week of Industrial Training

~5th April 2010~
Arrived at Zaidun-Leeng Sdn. Bhd. about 8.10am and went to the reception counter to report myself. Met with Ms. Josephine (account department) to get my access card (same as UNITEN ID where I have to tag in and out of the building to record my 'attendance').
Then, went to Infrastructure Department to report to Ir. Lim Guan Hock, Director of Infra Department. Ir. Lim brief us what I will get learn from this industrial training and then requested Ir. Peter Lim (an associate) to give me things to do and learn from it. Was then introduced to another engineer, Mr. Law Lok Heng. I will be helping Mr. Law on his on-going project includes Landfill, Double-Storey Terrace Housing, and much more. First thing I did was to design a RC Sump.

~6th April 2010~
2nd day, was requested to use AutoCAD to input borehole points of a site. Later was given a set of soil investigation test result to read through it, the SI method they used is the Soil Replacement Test and Field Density Test (FDT). Quickly finished it then went to help up another trainee with the cargo plane hanger project in Pulau Penang. We determine the ponding area of the hanger and calculate the area of it. It was simple but it takes time to complete it as we are not using any software to determine, all by hand and pen.

~7th April 2010~
Continue with the cargo plane hanger project, Ir. Lim requested us to draw a few cross section of the critical area to illustrate the level of ponding area. Later continue with the sump design which did'nt manage to complete it on monday.

~8th April 2010~
Started with identifying the cut and fill area which need on a hill top double-storey terrace houses on a contour layout plan, then transfer into the AutoCAD drawing by marking the cut/fill area with red and blue '-' & '+' signs. Then was asked to do correction of a double-storey house structural drawings using red pen. I learn how to read a structural drawing from it as well.

~9th April 2010~
Continue with the double-storey terrace houses structural drawings. After identifying the errors in the drawings, I was requested to check the beam and column of the structure to determine is over-design or otherwise. Minimum beam dimension usually used is 150mm x 300mm and steel bar of T12 for main reinforcement. I checked the beam which is not the minimum size to determine whether it needed such larger beam size. To determine it, I was told to identify the load distribution on the beam then calculate the moment and shear the beam is carrying and then check the beam size and steel bars size. If can reduce the size is better as it will reduce the overall construction cost.

*End of 1st week, holiday for 2 days ^^

Monday, March 22, 2010

Industrial Training

Company : Zaidun-Leeng Sdn. Bhd.

Date of confirmation : 11th December 2009

Industrial training period : 5th April 2010 - 25th June 2010

Working hours : 8.30am - 5.30pm

University : University Tenaga Nasional